Walton County – 01/21/26 – Walton County Public Works continues to make progress on ongoing infrastructure projects. The dedicated in-house crews have been hard at work on multiple infrastructure projects. Here are the key developments:
ORANGE BLOSSOM AVENUE (EAST AND WEST) DIRT TO PAVE
Project Improvements:
• Paving 0.26 miles extending from Brookside Drive to the end of maintenance
• Pavement striping
Current Status:
• Construction (stabilizing road base)
Traffic Impacts:
Intermittent shoulder and lane closures are anticipated throughout the duration of the project.
FOREST SHORE DRAINAGE IMPROVEMENTS
Project Improvements:
• Drainage system along Forest Shore Road
• Construction of a new sidewalk
• Installation of new sod in right-of-way
Current Status:
• Under Construction
General Information:
• This project was designed by Kimley-Horn
• This project is funded through the South Walton Infrastructure Funds and $400,000 from the Sidewalk Funds
Traffic Impacts:
Intermittent shoulder and lane closures are anticipated throughout the duration of the project.
ROADWAY IMPROVEMENTS ALONG NORTH SIDE OF CR 30A
Project Improvements:
• Asphalt apron installations along the 30A corridor. Work will take place at the following locations:
• Thyme Street: 150 feet
• Hickory Street: 125 feet
• Azalea Street: 100 feet
• Camellia Street: 100 feet
• Gardenia Street: 250 feet
• Montigo Avenue: 200 feet
• Live Oak, Nightcap, Holly, and N. Dothan Avenue: Apron work within the CR 30A right of way only.
Current Status:
• Under Construction
These improvements are part of ongoing efforts to enhance roadway safety, improve drainage, and support long-term infrastructure maintenance along the 30A corridor.
Traffic Impacts:
Intermittent shoulder and lane closures are anticipated throughout the duration of the project.
CR 30A MULTI-USE PATH RECONSTRUCTION FROM CR 395 TO SOMERSET BRIDGE (SEAGROVE)
Project Improvements:
• Installation of a new shared use path, drainage and shoulder improvements
Current Status:
• Under Construction
Please be advised that work will remain within established right-of-way limits.
Traffic Impacts:
During construction, you may observe workers, equipment, temporary traffic controls, and general activity typical of roadway and multi-use path construction.
W PARK PLACE OVERLAY
Project Improvements:
• The overlay operation will commence on W Park Place extending from S Walton Lakeshore Drive and will proceed for approximately .43 miles, terminating at the end of maintenance.
Current Status:
• Overlay completed
• Pavement striping
Traffic Impacts:
Intermittent shoulder and lane closures are anticipated throughout the duration of the project.
ADDITIONAL PROJECTS
• New LSV Lane: CR 30A and Deer Lake (base complete)
• New Agriculture Center (west off Hwy 90): Installation of mulch
• CR 1883-Drainage Improvements are 90% complete (awaiting headwall delivery)
• Eagle Springs Golf Course Entrance: Installation of new pipes and road base for the road
to the maintenance center. Mitered ends have been poured.
• Forest Shore Drive and N. Holiday Road: Asphalt Patching
• S. Norwood Road: striping crosswalks
• CR 30A @ Inlet Beach/SR 98 (Underpass): Prep/Sod installation
• Mack Bayou Road: Construction of new sidewalk
All activities are weather dependent and may be delayed or rescheduled in the event of inclement weather. Drivers are reminded to use caution when traveling through a work zone and to watch for construction workers and equipment entering and existing the roadway.
For more information, contact Public Works at (850) 892-8108.